City of Frontenac, Missouri

A Heritage of Gracious Living, Shopping and Dining

Geyer Road Revitalization Project Information

Greeting’s and Thank You for stopping by the 
Geyer Road Revitalization Project Information Site

Update for the Week of 03/17/2025

An unknown underground power service near West Geyer and Geyer Roads has slowed the progress as Ameren was unaware of its existence.  This power service is to be relocated by Ameren, however, due to the recent storms and damage it's unknown when Ameren will be back on site.

Update for the Week of 03/03/2025

The contractor (PCX Construction) is continuing to install stormwater piping and inlets along Geyer Road, the stormwater pipe installations will stop on Clayton Rd near the Bistate Bus Stop.

The placement of the new Sidewalk, Curb and Gutter, as well as driveway crossings are being placed at the same time, on the west side of Geyer Rd. This will hopefully speed-up the construction process barring any further weather delays.

This sidewalk project will connect to the sidewalk on the South Side of Clayton Rd. near the Spoede / Clayton Rd. intersection.

Update for the Week of 12/02/2024

The contractor (PCX Construction) is starting to install piping on Geyer Downs on Wednesday, Dec. 4, 2024.  Additionally, two (2) pipes were received today in preparation for this work.

As we receive updates on the project, we will continually add to this page.


The City of Frontenac has worked closely with East-West Gateway Council of Governments and Missouri Department of Highways to obtain federal funding to assist in the financial support of the Geyer Road Project for public safety and routes to schools.

MoDOT / Federal funding has advised “Concurrence” with the low bidder, PCX Construction and qualifications and compliance with federal regulations for the project due to the federal funding. This being said, they have a few required forms for the project to complete for the pre-construction meeting with the City and the Lochmueller Group, which will be scheduled soon. This project will push through winter as weather allows. Looking for a spring/early summer completion date. 

**As a reminder when waiting to maneuver through a one-lane closed flagmen-controlled section of roadway, DO NOT BLOCK INTERSECTIONS.** This will assist in keeping traffic moving as much as possible.

This project consists of pedestrian safety with installation of sidewalk along with stormwater improvements with street repaving.

The sidewalk will tie into the Clayton Road Sidewalk just west of the Clayton/Spoede Intersection on the South side of Clayton Road.

Continuing westbound to Geyer, crossing Geyer with a new signalized pedestrian signal, then turning south on the west side of Geyer.

The sidewalk will continue south at Hermitage Hill Road.

A special thanks goes out to all the property owners along the route for working closely with the City of Frontenac on the project.

Currently, Missouri America Water, Spire Energy, and Metropolitan Sewer District (MSD) have completed their projects prior to the start of this project.

Survey crews will be laying out the project as well as tree and brush removals, per agreements to begin. 

The official start date for construction is Monday, December 2.

Contact Us

Jeff Wappelhorst,
Director of Public Works

Public Works
10555 Clayton Rd
Frontenac, MO 63131
Get Directions

In this Department

More Information